Nix Library Update, 24 May 2022

This email arrived today:

“The roof at Nix is complete.

Internal repairs continues and should be completed by next week.

Next phase is cleaning/waxing of floors, commercial cleaning, restaging furnishings/equipment and return of staff in preparation of reopening.

Once the cleaning is scheduled our director will be able to offer an opening date.”

Nix Library Repairs Begin!

At last! Michel has let us know the following (the roof-plaster contractor is Battco):

“I am happy to report work is beginning this Friday, April 29th .  The schedule of work/tasks to be completed prior to re-opening to the public is as follows and subject to change.  We anticipate a reopening early June.

1.       Roof repair

2.       Internal plaster repair and painting  

3.       Floor stripping/waxing

4.       Commercial cleaning/dusting of interior”