15 May Update: SWB’s Turbine 4

SWB T4 (turbine 4) was supposed to start up again, or at least be installed, on 9 May. SWB has been testing it since then, perhaps delayed a bit by the troubles that caused our most recent boil-water advisory, I don’t know. They said Thursday that testing would continue through the weekend if necessary. The public has been told that the noise will be greatly reduced when it comes online.


Today, 15 May, we were told by Ghassan: “they are still relying on T1 and that ‘T4 tripped offline twice yesterday’.” He hopes that there is no need for the EMDs (diesel generators).

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: